They work on some of the UK’s major infrastructure projects and initiatives – and are also one of the UK’s largest regional builders, delivering on projects of all sizes and complexities.
We’ve worked with Kier Construction for several years on all sorts of projects – they trust us because we do what we say we’re going to do. For this project, we were working in the new border control buildings at Portsmouth International Port.
At Central, we have installation teams placed across the UK, enabling us to reduce our carbon footprint and costs for the client. Our team included a site supervisor, four experienced operatives and a contracts manager who visited site each week to check on progress.
We finished the project on time – and only had one small snag to deal with. Kier Construction were more than happy – plus, we picked up a few extra projects along the way.
We installed resin flooring throughout the entire space which was 2300m² + 1200 linear meters of coving.
Altrocrete HF polyurethane screed, which is perfect for creating a textured finish for heavy duty spaces. It’s durable and has resistance to slips, chemicals, including organic acids found in foodstuffs – so ideal for this food processing facility.
Concrete shot-blasting to properly prepare for the screed.
8-Weeks.